A very long interconnection for electricity and soaring material prices have caused the economy of the North Sea Energy Island to crumble which is already shaping up to be Denmark's largest, most expensive and most complex construction project in history.
SIGN UP FOR THE NEWSLETTER
Meanwhile, the government has recently managed to secure politi...
Experts: A mistake not to listen to the market about Energy Island North Sea 1.0
The 210 billion kroner project in the North Sea started off on the wrong foot as it failed to consult the market about the viability of the concept and the commercial feasibility of the tender conditions, according to observers

Until the end of 2022, Rambøll has been involved in "master planning" for the VindØ consortium which is one of the two known consortia bidding to build the North Sea Energy Island. Subsequently, Cowi has also been associated with the VindØ consortium. Henning Larsen Architects / VindØ-konsortiet
Få adgang til hele artiklen
- nemt og hurtigt
Prøveabonnement
Opret prøveabonnement
Opret nu
- Ingen kortoplysninger
- Ingen binding
Køb abonnement
Vælg mellem vores abonnementer til EnergyIslandNews, og find det, der passer dig og/eller dit firma
Se abonnementer